Power supply sequencing in spaceflight systems

Author : Oscar Mansilla, Senior Marketing Engineer at Renesas Electronics

02 July 2018

Intensive processing digital loads require multiple rails to power their circuitry, and the necessary devices demand very specific rail power-up and power-down sequencing to guarantee operational efficiency. Add the complexity of spaceflight operation and system designers have limited ways to implement the power sequencing requirements.

For the digital issue of this piece, please visit this link – or click here to register for EPDT's magazine.

Sequencing and monitoring power supplies can be accomplished in several ways. However, these implementations may not be suitable for spacecraft operating in the harsh deep space environment, or for satellites in Earth orbit.

This article describes the different sequencing solutions available to power system designers, and introduces a new radiation-hardened quad power supply sequencer that can be cascaded to sequence an unlimited number of power supplies. We will also review its fault monitoring capabilities and examine how the total ionising dose (TID) and single event effects (SEE) experienced during spaceflight can damage integrated circuits.

Implementing sequencing

The most basic way to implement sequencing is to utilise the power good (PG) and enable (EN) pins of the point-of-load (POL) or low dropout (LDO) regulator. Figure 1 (above) shows that the PG pin of converter ‘n’ will be connected to the EN pin of converter ‘n+1’. This cascading configuration is repeated for all the rails in the system. To add a delay between the PG signal asserting and the startup of the next regulator in the sequence, a capacitor is added to the EN pin of the next regulator.

This is by far the simplest method and is essentially cost free; however, it does have major drawbacks. The biggest is that it does not support power down sequencing in the reverse order. Other drawbacks include the variation of the PG assertion level and the PG delay versus temperature. Figure 2 shows that the PG delay across the temperature range can shift by a factor of two, preventing the proper design of delays between the sequenced rails.

While a discrete solution implementation that uses comparators, resistors and capacitors can provide power-up sequencing, this method still does not allow power-down in the reverse order (see Figure 3). The added complexity does include the benefits of precision voltage monitoring and the ability to delay both the power-up and power-down. However, the discrete design increases the solution size and the bill of materials cost.

The two previous methods have one common flaw: the inability to power down in the reverse order, which may be needed to ensure system reliability. For example, high-end FPGAs require that the rails for the core, auxiliary and I/O voltages power down in reverse order to avoid both excessive current draw and possible damage to the costly digital load. To meet the power-up and power-down requirements, the new ISL70321SEH radiation-hardened quad power supply sequencer may be used.

Credit: Shutterstock

The benefits of using an analogue power sequencer include both its effortless design, with minimal external components, and its accurate fault monitoring to ensure reliable system operation. A timing diagram showing the power-up and power-down sequencing is presented in Figure 4.

Figure 5 illustrates an application schematic using the ISL70321SEH to sequence the core, auxiliary and I/O voltage rails required for a typical high-performance FPGA. A resistor divider connected from power supplies to the corresponding voltage monitor (VM) pin is all that is needed to monitor each rail. This divider also sets the turn-on and turn-off voltage of the next sequenced device. The simple open drain EN outputs make it easy to drive voltage regulators with different enable thresholds.

Programmable rising and falling delays are easily achieved by use of a single external resistor. This delay can be programmed between 2ms to 20ms. A power good timer is also included to detect if a rail does not come up within a programmed window of time from 4ms to 40ms.

In addition to sequencing, the ISL70321SEH has active monitoring of over half a dozen fault conditions to ensure reliable power system operation. These include:

- Sequence order fault

- Brown out fault

- PGOOD fault

- Input fault

- Output fault

- Externally triggered faults

Credit: Vladi333/Shutterstock

For more complex multi-rail power systems, such as those in RF applications – where the number of rails can easily exceed more than a dozen – the ISL70321SEH can easily be cascaded to sequence virtually an unlimited number of rails. Figure 6 highlights the necessary common connections to sequence 12 power supplies, using three ISL70321SEH sequencers. Through the use of the UP, INIT and DONE pins, cascaded devices communicate to achieve power-up and reverse power-down sequencing of all the rails.

Operating in space

Space radiation effects on electronic devices are an important system design consideration. They can cause problems ranging from operational malfunctions to severe physical damage to the devices.

Total ionising dose (TID) and single event effects (SEEs) are two of the most common effects that cause damage to an integrated circuit. TID effects are the result of accumulated exposure to ionising radiation. SEEs, which are the result of a single high energy particle that strikes the device, can cause a transient on output of a circuit. This is known as a single event transient (SET). However, they can also be destructive, causing single event burnout (SEB) or single event latch-up (SEL).

The ISL70321SEH is designed to operate in the harsh space environment. Assurance TID testing on the ISL70321SEH is done to 75krad(Si) at 0.01rad(Si)/s and 100krad(Si) at 50-300rad(Si)/s under biased and grounded conditions. SEE testing results show no SEL or SEB for ions with LET = 86.4 MeV•cm2/mg with Vdd = 14.7V. No SETs were detected for LET = 20 MeV•cm2/mg.

Conclusion

With the arrival of the industry’s first space QML-V qualified radiation-hardened power supply sequencer, spacecraft system design engineers will now be able to implement a simple, accurate and scalable method to achieve the proper power-up and power-down sequencing of DC/DC converters in highly dense multi-rail power systems.

Armed with the knowledge that power supply performance will not falter under the harsh environment of space, designers can implement as many power supplies as needed for their spacecraft.


Contact Details and Archive...